Operator: Neptune Energy Norge AS
Production licence: 153
Facility: Deepsea Yantai
Field: Gjøa
Duration: 240 days
Other info: The consent applies to production drilling on the Gjøa field using the Deepsea Yantai mobile drilling facility. The facility is a semi-submersible drilling facility operated by Odfjell Drilling AS. The facility was built at the CIMC Raffles yard in China and was completed in 2016.
Deepsea Yantai received an Acknowledgement of Compliance (AoC) from the PSA in November 2019.
Gjøa
Gjøa is a field in the northern part of the North Sea, 50 kilometres northeast of the Troll field. The water depth in the area is 360 metres. Gjøa was discovered in 1989, and the plan for development and operation (PDO) was approved in 2007. The field is developed with four subsea templates and one satellite well tied-back to a semi-submersible production and processing facility. Production started in 2010.
Source: norskpetroleum.no