Operator: Lundin Energy Norway
Production licence: 338
Facility: Rowan Viking
Field: Edvard Grieg
Duration: 265 days
Edvard Grieg
Edvard Grieg is a field in the Utsira High area in the central North Sea, 35 kilometres south of the Grane and Balder fields. Water depth in the area is 110 metres. Edvard Grieg was discovered in 2007, and the plan for development and operation (PDO) was approved in 2012. The field has been developed using a fixed installation with a steel jacket and full process facility. A jack-up rig is utilised for drilling and completion of wells. Production began in 2015.
Source: norskpetroleum.no