In August 2019, Vår Energi received consent to use the Island Constructor well intervention facility for well intervention on the Goliat field in the Barents Sea

Find out more: Vår Energi – Consent for use of Island Constructor – Goliat field (19 August 2019) 

The consent has been extended to include intervention on wells 7122/7-B-4 Y1H/Y2H, 7122/7-C-3 Y1H/Y2H, 7122/7-C-2 H and 7122/7-B-3 H.

The work is scheduled to begin in September 2019.

The Island Constructor well intervention facility is operated by Island Offshore Management AS (Island Offshore). The facility was issued with Acknowledgement of Compliance (AoC) by the PSA in 2010.