The audit was carried out from 13 to 15 February 2023.

Objective

The objective of the audit was to monitor how the company complies with the regulatory requirements for electrical facilities, and work in and operation of electrical facilities.

Result

Five non-conformities were identified, concerning:

  • Marking of pressurised rooms
  • Safety function for monitoring overpressure in pressurised rooms
  • Protection against energisation
  • Implementation of necessary preventive measures for emergency lighting
  • Documentation of selectivity in UPS installation

In addition, an improvement point was identified relating to arcing analysis.

What happens next?

We have asked Gassco to report to us on how the non-conformities will be addressed and for their assessment of the improvement point identified. The reply deadline is set at 14 April 2023.