The audit was conducted from 15 November 2022 to 12 January 2023.

Objective

The objective of the audit was to investigate how Equinor meets the requirements for technical safety, the working environment, fire insulation, the handling of corrosion under insulation (CUI), and the collection of environmental data.

Result

No non-conformities were identified.

Five improvement points were identified, relating to:

  • Chemical working environment
  • Noise
  • Flange tag information requirements
  • Collection of environmental data
  • Temporary insulation

What happens next?

We have asked Equinor for their assessment of the improvement points identified. The reply deadline is set at 28 February 2023.