The audit was conducted on 18 and 19 May 2021.

Objective

The objective of the audit was to verify Equinor’s management and follow-up of emergency preparedness in connection with preparations for operation, and that these comply with the company’s and the authorities’ requirements.

Result

Two improvement points were identified during the audit. These concerned:

  • Internal handling of non-conformities
  • System for training and drills

What happens now?

We have asked Equinor for their assessment of the improvement points observed. The deadline for this is set at 16 August 2021.