The audit was conducted on 2 June 2020 and focused on the company’s arrangements for and implementation of project management and activities relating to the upgrading and life extension of Jotun A.

Objective

Our objective was to verify that, through its project management and project follow-up, Vår Energi is reducing risk and preventing accidents during start-up and in the operational phase.

Result

No non-conformities were identified during the audit.

Four improvement points were identified in connection with:

  • Dissemination of information and reporting
  • Analyses
  • Design to counter green water events
  • Compliance with the requirements in NORSOK N-004

What happens now?

We have asked Vår Energi to give us their assessment of the improvement points we observed by 24 August 2020.