Objective
The objective of the audit was to verify how Statoil is organising the proper planning and execution of the scaffolding work.
Result
Seven non-conformities were identified in connection with:
- Incorrect use of suspended platforms in the installation
- Own control of scaffolding in the installation
- Supervisory duty relating to scaffolding in use
- Maintenance of scaffolding materials
- Training of personnel
- Risk assessments
- Transfer of experience and learning from incidents
In addition, four improvement points were identified in connection with:
- Training
- Language of labelling
- The scaffolding manual
- Governing documentation