§ 85 Well barriers
During drilling and well activities, there shall be tested well barriers with sufficient independence.
If a barrier fails, activities shall not be carried out in the well other than those intended to restore the barrier.
There shall be pumping and fluid capacity available on the facility or on vessels in the event of heavy well intervention. The need for pumping and fluid capacity in the event of light well intervention shall be included in the activity-specific risk assessment.
When handing over wells, the barrier status shall be tested, verified and documented.