§ 84 Monitoring well parameters

During all drilling and well activities, drilling and well data shall be monitored and collected to verify the well prognoses, so that necessary measures can be implemented and the well programme adjusted if necessary.
Section last changed: 01 January 2011

The requirement relating to collection implies, inter alia, that data that could indicate a possible well control incident, are monitored, recorded and processed.
In order to fulfil the requirement relating to collection, the NORSOK D-010 standard, Chapters 5.7, 6.7.3 and 6.7.4 should be used, with the following addition: when testing the formation's fracture strength, pressure testing to the maximum anticipated pressure for the well section should be carried out.