The objective of the audit was to monitor that CoPSAS’s management of maintenance, including its own follow-up of ongoing changes that affect such management, comply with the authorities’ and the company’s own requirements.
There was a further aim of monitoring that efforts to improve the management of maintenance ensure that key contributors to HSE risk are identified and followed up.
Result
Three non-conformities were identified in connection with:
In addition, four improvement points were identified relating to:
What happens now?
We have asked CoPSAS to report on how the non-conformities will be addressed. We have also asked the company for feedback that assesses the improvement points we observed.
The deadline for this is set at 27 February 2019.
Øyvind Midttun, press contact